IEC 62676-4:2025 lists user acceptance testing, commissioning and handover (clause 15.3) and final documentation (clause 16) as separate steps. A factory sign-off should therefore cover 14 checks: NTP time from NIC/NPL, retention measured in days, a 24×7 schedule, the night image, PoE headroom, changed passwords, certified firmware, ONVIF/RTSP, earthing, labels, as-built drawings and sealed credentials.

Verified against

Commissioning checklist: how to check and what passes

Menu paths are from the CP Plus manuals. Other brands use different paths for the same checks.

# Check How to check Pass criterion Source
1 Time zone and NTP Camera: System > General > Date & Time. NVR: Manage > System > General > Date&Time, then Manual Update GMT+05:30, NTP on, server is samay1.nic.in/samay2.nic.in or time.nplindia.org (or a plant server synced to them). Not the NVR's offered time.windows.com/time.google.com CERT-In Direction (i), FAQ; NPL; CP Plus NVR §4.4.1.2
2 Camera clocks follow NVR NVR Manage > System > General > Basic: CAM Time Sync and Interval On. The manual says only that it "syncs the Device time with the IP camera", so confirm the result: the time overlay on every channel matches the NVR CP Plus NVR §4.4.1.1
3 Retention in days Manage > Storage > Disk Quota: Record Duration (Days) per channel. Manage > Storage > Basic: Disk Full Days ≥ contract figure on every channel. Disk Full = Overwrite. At day N+1, the oldest clip on the timeline is N days old MeitY OM (xv); CP Plus NVR §4.3.1, §4.3.7
4 Auto-delete not shorter than contract Manage > Storage > Basic: Auto Delete Old Files Never, or Custom ≥ contract days. Deleted files "cannot be recovered" CP Plus NVR §4.3.1
5 Recording schedule Manage > Storage > Schedule > Record. Use Copy to apply to all days Continuous 24×7 on every channel unless the contract says otherwise. If cameras have SD cards, ANR is on CP Plus NVR §4.3.2.1
6 Night image Visit during the night shift. Check Camera > Image > Day/Night (ICR or Electronic) and Illuminator. Hold a test chart at the agreed distance The agreed pixel-density level is reached at night on recorded footage, not just live view IEC 62676-4:2025 §13.3.2, Annex C; CP Plus camera §4.3.1.7, §4.3.1.9
7 50 Hz anti-flicker Camera > Image > Exposure > Anti-flicker 50Hz on indoor cameras under LED or tube lights. No rolling bands CP Plus camera §4.3.1.4
8 PoE budget Add up each camera's datasheet maximum draw (IR on) per switch. Compare with the switch's PoE budget and port class Each camera within its class: 802.3af ≤ 12.95 W at the device, 802.3at ≤ 25.5 W. Total under the switch budget. No port drops during the night test Cisco PoE table
9 Default passwords Try admin/admin and blank logins on the NVR and three sample cameras All fail. Cameras auto-initialised over the NVR's PoE ports "adopt the current password" of the NVR, so change them if the contract asks for unique passwords MeitY OM (vii); CP Plus NVR §4.1.1
10 Firmware Camera: System Info > Version The firmware version matches the one on the model's ER test report or STQC certificate. Under MeitY's series guidelines, each firmware version is a separate series CP Plus camera §4.8.1; MeitY Series Guidelines; MeitY OM (viii)
11 ONVIF for analytics CP Plus: Network > Platform Access > ONVIF. Hikvision: Configuration > Network > Advanced Settings > Integration Protocol ONVIF on, with a separate ONVIF user and a password you hold. A third-party ONVIF client lists every camera CP Plus camera §4.4.10.1; Hikvision ONVIF how-to
12 RTSP stream Network Settings > Port: RTSP port (CP Plus default 554). Open rtsp://<user>:<pass>@<ip>:554/cam/realmonitor?channel=1&subtype=0 (and subtype=1) in VLC Main and sub stream open on sample cameras with a non-admin account CP Plus camera §4.4.2
13 Earthing and surge Have your electrician inspect the NVR socket. On outdoor or roof runs, trace the cable to the surge protector NVR (a Class I appliance) on a socket with protective earth. Outdoor runs: surge suppressor "as close to the camera as possible", shielded cable and RJ45, all bonded to one bus bar CP Plus NVR safety section; Bosch/Keenfinity
14 Labels, drawings, logs, credentials Walk five random cameras from the drawing to the switch port. Export INFO > Log (.csv) Each label matches the as-built drawing (camera ID, IP, switch port). The handover file has the drawings, a per-camera commissioning record and an operating logbook. Admin credentials are handed over sealed; the integrator keeps a named, role-based account IEC 62676-4:2025 §15.3, §16.2, §16.3, §16.5; MeitY OM (xiv); CP Plus NVR §4.13.1

No document we read sets a clock tolerance in seconds, so write your own figure into the contract. This page is the how-to-verify side: the contract wording, plus codec/bitrate and internet-exposure checks (UPnP, P2P, outside port scan) not repeated here, are in our tender specification template.

Where brands and documents differ

What breaks in a factory

When to call the installer / what to ask the vendor

Withhold the final payment until rows 1–14 are signed. Ask the installer for the as-built drawing as an editable file, a per-camera sheet (ID, IP, MAC, switch port, firmware) and the ER/STQC evidence for each model. Brand-specific NTP and reset steps are on the CP Plus setup page.

Where Mama fits

Rows 11 and 12 decide whether your cameras can feed analytics later. Mama reads existing cameras over RTSP/ONVIF and tells the owner where machines sat idle yesterday. Leave an email or phone in the form below.

FAQ

What is checked during CCTV commissioning? Time sync, the recording schedule, retention in days, image quality by day and night, power, security settings and the documents: drawings, a per-camera record and credentials. IEC 62676-4:2025 treats acceptance testing, commissioning and handover (15.3) and final documentation (16) as separate steps.

Which NTP server should CCTV in India use? CERT-In's directions require body corporates to sync ICT clocks to NIC or NPL NTP servers, or to servers traceable to them. Its FAQ lists samay1.nic.in, samay2.nic.in and time.nplindia.org.

How do I check how many days my NVR actually stores? Look at the date of the oldest recording on the playback timeline. On CP Plus NVRs, also check Record Duration (Days) under Manage > Storage > Disk Quota.

Should ONVIF be left on after handover? Leave it on only if an NVR, VMS or analytics tool uses it, behind a separate ONVIF password. CP Plus's NVR manual advises disabling unneeded services.

Last verified 13 Oct 2026 against the vendor and regulator documents listed above. Found an error? Tell Mama in the form below.

Read next
Free · no obligation

Get a camera plan for your floor

Tell Mama about your plant and Mama will come back with how many cameras you need, where they go, and the retention your state expects — sized to your floor, in ₹. Built for Indian factories.

  • How many cameras & exact placement
  • Compliance-ready (BIS/STQC, women's night shift)
  • Honest ₹ estimate — guard vs camera-AI

Mama replies by email or phone — whichever you left. No spam, no obligation.