Is Resin Going Missing? Reconcile Granules Issued vs Parts Made in a Moulding Shop (₹)

Is Resin Going Missing? Reconcile Granules Issued vs Parts Made in a Moulding Shop (₹)

By The Mama Editorial Team · Factory-floor cameras, India compliance & operations

Is resin going missing between your store and your presses? Check it monthly: kilos issued against good parts, material sent out and floor stock. As of 15 Oct 2026, an IOCL distributor list puts injection-moulding PP at ₹1,57,952 a tonne in Thane, before GST. At that price, an unexplained 2% gap in our 20-press example costs about ₹3.1 lakh a month.

Last checked: 17 Oct 2026

By the Mama Editorial Team. This piece is for owners of Indian injection-moulding shops making closures, containers, housings and technical parts. Every figure from a published source carries its date and link. Our own inputs are marked "assume". This is a reconciliation, not an accusation: a gap can come from measurement as easily as from loss.

Key takeaways

How this differs from a scrap-cost calculation

Our guide to regrind and scrap costs in a moulding plant and the regrind, runner and scrap calculator price the plastic you know about: runners, purge, start-up shots and rejects.

This page asks a different question. Does every kilo issued from the store end up somewhere you can weigh? Scrap is a known loss. A reconciliation gap is material you can't place at all.

The same logic works in other trades. Garment owners can follow it in our piece on fabric and trims issued vs consumed.

The mass balance on one page

Treat the moulding floor as a box with one door from the store and one door to finished goods. Over a month, weight goes in and weight comes out. What comes out includes what is still sitting inside at the end.

In:

Out:

Gap = In − Out. Express it as a percentage of granules and masterbatch issued in the month.

Two rules keep the balance honest. First, never add reground runners and rejects as an output if they went back into the hopper; they appear later as parts or as closing regrind stock. Second, the opening and closing floor counts must be done the same way, at the same time of day, by the same person.

A worked example: a 20-press PP shop

Assumptions (illustrative, replace with your own):

Line Kilos (kg) Where the number comes from
Virgin PP issued 96,000 Store issue slips
Masterbatch issued 1,900 Store issue slips
Opening floor stock (regrind 2,100 + hoppers, dryers, part bags 600) 2,700 Weighed on the 1st
Total in 1,00,600
Good parts (count × standard weight, all moulds) 91,442 FG receipts × part weight card
Regrind and lumps sent to scrap store 2,900 Weighed at scrap store
Purge and sweepings 650 Weighed per shift
Rejects in quarantine 350 Weighed
Closing floor stock (regrind 2,600 + hoppers, dryers, part bags 700) 3,300 Weighed on the last day
Total out 98,642
Gap 1,958 (2.0% of 97,900 kg issued)

At ₹158/kg, 1,958 kg is ₹3,09,364 a month, or about ₹37 lakh a year. Spread over 20 presses, that is about ₹15,500 a press a month.

The same shop at other gap levels:

Gap (% of issued) Kilos per month (kg) ₹ per month at ₹158/kg
0.5% 490 77,341
1.0% 979 1,54,682
1.5% 1,468 2,32,023
2.0% 1,958 3,09,364
3.0% 2,937 4,64,046

Prices move. IOCL rolled PP prices over unchanged with effect from 15 October 2026 (Plastemart price news, checked 17 Oct 2026). Reliance's PP circular of 1 Oct 2026 (ref. 2026-27/PP/DTA/026) lists its grade H110MA at ₹1,60,035/MT delivered in Pune, GST extra, with a cash discount of ₹1,100/MT. Use your own landed price from last month's invoice.

Tolerance bands: when a gap is noise and when it is a question

We found no published Indian norm for a permitted resin reconciliation gap in a moulding shop on the CIPET or AIPMA websites (checked 17 Oct 2026). The bands below are our assumption, set so that measurement error stays inside the first band. Tighten them once you have six months of your own data.

Gap (% of issued) Assumed reading What to do
Under 0.75% Measurement noise Record it, change nothing
0.75% to 1.5% A standard or a count is off Run the six checks below
Over 1.5% Material is leaving unrecorded, or a big count error Checks, plus a review of how material leaves the store and the floor
Negative (more out than in) Parts are overcounted or issues are under-recorded Check cavity counts and issue slips first

A negative gap is as useful as a positive one. It means parts are overcounted or issues went unrecorded, and either can hide a real gap.

Six checks that explain a gap before anyone is blamed

1. The standard part weight is stale. The weight on the part card was set when the mould was new. A worn tool, a changed packing pressure or a heavier wall can make parts heavier without anyone noticing. In the example, parts 1% heavier than standard would explain 914 kg, almost half the gap. Weigh 20 parts per mould each week and update the card.

2. Cavities are counted wrong. If good parts are counted as shots × cavities, a blocked cavity breaks the count. On an 8-cavity mould with one cavity blocked, the count overstates output by one part in eight. That makes the gap look smaller than it is, or even negative.

3. Purge and sweepings are not weighed. Night-shift purge often goes into a bag that nobody weighs. Every unweighed kilo lands in the gap. Weigh it per shift, even roughly.

4. The scales disagree. The store issues on one scale and the floor weighs on another. Check both against the same known weight once a month, and check-weigh ten 25 kg bags from each lot.

5. Moisture leaves as steam. Hygroscopic grades lose weight in the dryer. One ABS injection grade lists 0.22% moisture at 23 °C and 50% relative humidity (ISO 62), dried to below 0.05% at 80 °C for 2 to 4 hours (Bada BADALAC ABS 20 datasheet, issue date 16.01.2019). That is up to about 0.17% of weight if granules arrive at that moisture. It matters for ABS, nylon or PC, not much for PP. For an assumed 20 tonnes of ABS a month it is about 34 kg.

6. Floor stock is guessed, not weighed. If the closing count is "about ten bags", the gap moves with the guess. Weigh it.

Only when these six are clean does the remaining gap point at the store and the gate. The raw material store CCTV specification shows how to set up the issue counter so each slip can be checked against what physically left.

Why the money is bigger than the kilos

The gap costs more than resin.

What a camera can and cannot tell you here

A camera cannot:

A camera can show:

The pairing that works is a scale for the kilos, a register for the slips and video for the times. Our camera guide for injection-moulding units covers the press-side views.

On people: this is about material flow, not about watching operators. Review footage of doors and counters, not of individuals at work. Footage of recognisable workers is personal data under s.2(t) of the DPDP Act, 2023; tell workers in writing what is recorded and why (see the worker CCTV notice under DPDP).

Running the reconciliation every month

A routine that takes about two hours a month:

  1. On the last working day, weigh all floor stock: regrind bags, part bags at presses, hoppers and dryers (or estimate those from the level mark, the same way every month).
  2. Total the month's store issue slips for granules and masterbatch.
  3. Pull good-part quantities from FG receipts, not from shot counters, and multiply by this month's checked part weights.
  4. Total the weighed scrap, purge, sweepings and quarantine.
  5. Work out the gap and its percentage, and write it on one line in a register with the date.
  6. If it is above your band, run the six checks in order before anything else.

Where Mama fits

Mama reads the cameras a factory already has and sends the owner a short plain-language note each morning about where press-hours went the day before. It covers presses that stood idle, long purges and colour changes, and stoppages that clustered on one shift. It watches machines and material flow, not individual workers. It doesn't weigh resin or replace the store register. If you'd like Mama to look at your floor and suggest where cameras would earn their keep, leave an email or phone in the form below.

FAQ

How do I calculate resin consumption against parts produced? Multiply good parts by the checked part weight for each mould, add weighed scrap, purge, quarantine and closing floor stock, and compare that with granules issued plus opening floor stock. The difference is the gap. Express it as a percentage of the month's issues.

What reconciliation gap is acceptable in an injection-moulding shop? We found no published Indian norm on the CIPET or AIPMA websites (checked 17 Oct 2026). As a working assumption, treat under 0.75% as measurement noise, 0.75% to 1.5% as a count or standard to check, and over 1.5% as a question about how material leaves the floor. Tighten the bands once you have your own history.

Should regrind be counted as an output? Only the regrind that left the floor (sold, sent to the scrap store) or sits on the floor at month-end. Regrind that went back into the hopper turns up later as parts, so counting it as output double-counts it.

Why is my gap negative? Either good parts are overcounted, for example shot counter × cavities on a mould with a blocked cavity, or some issues were made without a slip. A negative gap can hide a positive one.

What does a 2% resin gap cost? In our 20-press example, 2% of 97,900 kg issued is 1,958 kg. At ₹158/kg, based on IOCL's PP list price of 15 Oct 2026, that is about ₹3.1 lakh a month, before any lost GST credit.

Read next
Free · no obligation

Get a camera plan for your floor

Tell Mama about your plant and Mama will come back with how many cameras you need, where they go, and the retention your state expects — sized to your floor, in ₹. Built for Indian factories.

  • How many cameras & exact placement
  • Compliance-ready (BIS/STQC, women's night shift)
  • Honest ₹ estimate — guard vs camera-AI

Mama replies by email or phone — whichever you left. No spam, no obligation.