SMETA, amfori BSCI and WCA Audits: What Auditors Check on Hours, Overtime and Attendance Records (India)

SMETA, amfori BSCI and WCA Audits: What Auditors Check on Hours, Overtime and Attendance Records (India)

By The Mama Editorial Team · Factory-floor cameras, India compliance & operations

In a social audit, working hours are tested mostly on paper. The auditor pulls three months of time and wage records for a sample of workers, one of them your peak month, and checks them against production, shipping and worker interviews. Most hours findings come from records that don't agree with each other, more than from any single long day.

By the Mama Editorial Team, for owners of Indian export units who face SMETA, amfori BSCI or Intertek WCA audits through their buyers. Audit points come only from Sedex, amfori, ETI or Intertek documents; legal points from the Labour Codes and Rules. Not legal advice.

Key takeaways

The rulebook: law first, then the code, and the stricter one wins

SMETA (Sedex). The current methodology is SMETA 7.0, released in June 2024. It audits against the ETI Base Code plus local law. A gap against Indian law is a non-compliance. A gap where you meet the law but miss the Base Code is a non-conformance. Findings are graded Business Critical to Minor; there is no pass or fail.

The ETI Base Code, clause 6 sets the hours rules:

amfori BSCI. The Code of Conduct (2021) commits suppliers to no more than 48 standard hours a week. Overtime has to be "exceptional and voluntary", paid at a minimum of 125%, and never beyond the limits in national law. Workers get daily rest breaks and one day off in seven. The audit has 81 questions across 13 Performance Areas, each rated A–E. Performance Area 6 (Decent Working Hours) has four questions, and three of them are crucial. Fair Remuneration (PA 5) tests wages and deductions. A C rating or below can trigger a follow-up audit and brings the next full audit forward to one year instead of two.

Intertek WCA. Intertek's public pages list "Wages & Benefits, Working Hours" and "Documentation and Records" among the areas assessed. The detailed protocol isn't public; ask your auditing office for the checklist.

Indian law. The OSH Code took effect on 21 November 2025. It limits a worker to 8 hours a day and 6 days a week. Overtime needs the worker's consent and is paid at twice the rate of wages, which is basic plus DA, not gross pay. For a factory, your state makes the working rules on spread-over, breaks and the quarterly overtime ceiling. Where your state hasn't notified its own rules under the Code, its old factory rules broadly continue during the transition. The Central OSH Rules set 144 overtime hours a quarter for central-sphere establishments. Check your state's figure.

So an Indian unit lives with four limits: 48 normal hours, overtime at 2× (basic + DA), your state's overtime cap, and the Base Code's 60 total hours a week.

How an auditor actually tests hours

Sedex's Minimum Requirements bind SMETA auditors. We found no public copy on sedex.com; the link is a copy published by the audit firm VWA. What matters for your time office:

Timing. Audits happen when at least 60% of the peak workforce is present and the site is in full operation, not in the low season. Sedex's opening-meeting checklist (SMETA 7.0 Auditor Manual, Annex 5, VWA copy) has the auditor confirm your peak production periods and sample hours from them.

Which records. 12 months must be available for an initial audit (3 if the site is new); for a periodic audit, at least 3 months since the last one. Records missing without a legitimate reason are recorded as a non-conformance.

How many workers. The file sample grows with headcount:

Workers on site Worker files reviewed Wage + hour records (× 3 months)
101–500 26 78
501–1,000 42 126
1,001–2,000 52 156

Source: Sedex Minimum Requirements v1.2, auditor-day table.

Wage and hour months should match. Where a local waiver allows annual overtime hours, the auditor also checks 12 months of hours for at least five workers.

Triangulation. Evidence is cross-checked across documents, interviews and the site tour. On hours, the guidance names the records compared: "production records, payroll records, shipping records and working hours records". If March's register shows no overtime but March's shipments couldn't have been made in 8-hour days, that gap is a finding.

Interviews cover different shifts, every pay grade, and workers whose records show specific issues.

The non-conformities the guidance itself points at

Limited to what the Sedex, amfori and ETI documents name:

  1. Total hours above 60 in a 7-day week, usually in the peak month, even when every overtime hour was paid at 2×.
  2. No day off in seven days during a dispatch push.
  3. Overtime that isn't voluntary, for example a standing instruction that the line stays until the target is met. amfori asks for overtime to be "exceptional and voluntary".
  4. Overtime paid below the legal rate, for example 2× on basic only, or a flat allowance (a non-compliance against Indian law).
  5. Piece-rate pay that doesn't reach the minimum wage within standard hours. amfori's Code says this explicitly.
  6. Deductions not authorised by law. Both amfori (PA 5, a crucial question) and the ETI Base Code bar them.
  7. Manual registers with ticks instead of in/out times, or not signed by workers each pay period.
  8. Records that disagree with each other: production against hours, payroll against attendance, gate logs against overtime registers. The same Annex 5 checklist says Sedex members would rather work with a site on excessive overtime than see "hours of work could not be verified" because of inconsistent records.

Sedex states that members "will likely consider falsified or withheld information as a serious non-conformance". Honest records of 58 hours in a peak week beat records of 48 that nobody believes.

Keeping your records consistent under the Labour Codes

The Central OSH Rules (r.72, binding central-sphere establishments) show the Code-era register set: an employee register, an attendance-register-cum-muster-roll, and a register of wages, overtime and deductions, kept electronically or otherwise and preserved for five years. Your state's forms may differ. Then build these habits:

Our overtime cost calculator handles the 2× arithmetic, and Can Your Sewing Floor Take a 50,000-Piece Order? covers capacity from SAM.

Worked example: does March's output fit March's register?

The auditor's production-against-hours check, done by you first. Every number is an assumption; use your own SAM, efficiency and your state's current minimum-wage notification.

Assume: one sewing line, 40 operators, 26 working days. The register shows 8-hour days and no overtime. The style SAM is 20 minutes, and 16,000 pieces were packed in March. Wages (basic + DA) are assumed at ₹15,600 a month. So the daily rate is ₹600 (1/26), the hourly rate is ₹75, and the overtime rate is ₹150 an hour at 2×.

Step Line efficiency 55% (line's usual) Line efficiency 50%
Standard hours earned (16,000 × 20 min ÷ 60) 5,333 h 5,333 h
Operator-hours needed (÷ efficiency) 9,697 h 10,667 h
Operator-hours on register (40 × 8 × 26) 8,320 h 8,320 h
Hours the register doesn't explain 1,377 h 2,347 h
Per operator per working day ≈ 1.3 h ≈ 2.3 h
Implied weekly total (48 + 6 × daily OT) ≈ 56 h ≈ 61.5 h
Cost to record and pay it at ₹150/h ≈ ₹2.07 lakh ≈ ₹3.52 lakh

At 55% the gap is a records problem: the work fits inside 60 hours, so record the overtime, take consent and pay ₹2 lakh a month on this line. At 50% it is a capacity problem: even fully paid, the hours break the 60-hour line, and you need more operators, another line or a different promise to the buyer. amfori's own guidance names capacity planning and short-notice order changes as root causes of long hours.

Where cameras help, and where they don't

None of the documents we read requires CCTV: Sedex's Minimum Requirements and Annex 5, the ETI Base Code, and amfori's Code and rating guide. (Intertek's full WCA protocol isn't public.) Sedex asks auditors to photograph non-compliances and infrastructure, but the pictures must "not infringe privacy or data protection requirements" and workers' faces and names must be obscured. Don't install cameras "for SMETA".

Existing cameras can give an aggregate view: whether a line was active after the shift bell, how many stations ran at 7:30 pm, whether the floor worked on the weekly off-day. It is the auditor's cross-check, run daily, so gaps surface while you can still fix the register, consent and pay.

What video cannot tell you:

If you use footage at all, keep it to line-level counts, give workers the DPDP notice, and never rank individuals; per-worker tracking undermines discipline more than it fixes it.

Where Mama fits

Mama reads the cameras a plant already has and sends the owner a short note each morning about the machines and lines: which ran past the shift end, which sat idle, and where hours leaked. It watches machines and flows, not named people, so evening running is a line-level fact to check against your overtime register. Mama doesn't produce audit evidence or replace your registers. Mama can draw a camera plan for the lines that run past the shift bell. Leave an email or phone in the form below.

FAQ

Does SMETA or amfori BSCI require CCTV in the factory? Not in the Sedex, ETI or amfori documents we read. If someone says "CCTV is mandatory for SMETA", ask for the clause.

How many months of attendance and wage records will a SMETA auditor ask for? Twelve months must be available for an initial audit (three if the site is new). The auditor reviews at least three of them, including your peak month, for a sample sized by headcount.

Is the ETI 125% overtime premium enough in India? No. SMETA applies the higher standard, and Indian law requires twice the rate of wages (basic plus DA). The 125% is only a Base Code recommendation.

Can we keep a manual muster roll? Sedex auditors accept manual attendance records if they show actual time-in and time-out and are signed by workers once per pay period. Ticks or symbols aren't accepted. Your state's rules decide the register format.

What happens if our peak month exceeds 60 hours a week? It is a Base Code finding even if the overtime was paid and lawful, unless every clause 6.5 condition is met. An honest record leads to a corrective action plan; a hidden one risks being treated as falsification.

Read next
Free · no obligation

Get a camera plan for your floor

Tell Mama about your plant and Mama will come back with how many cameras you need, where they go, and the retention your state expects — sized to your floor, in ₹. Built for Indian factories.

  • How many cameras & exact placement
  • Compliance-ready (BIS/STQC, women's night shift)
  • Honest ₹ estimate — guard vs camera-AI

Mama replies by email or phone — whichever you left. No spam, no obligation.